The following check-list provides the details of the action
needed at various levels- from booking office to the delivery office- for
successful functioning of the software:
Office
|
Action
|
Pre requisite
|
Procedure
|
Booking Office
|
Office creation
(if not a Post Office)
|
Download the format to add office from https://services.ptcmysore.gov.in/ParcelNet->downloads
|
|
Ebiller ID creation (if COD customer)
|
The Divl. Administrator of Postal
Division has to create this. The Customer details are to be mentioned while
registering COD biller. The Delivery Post Office concerned of the PIN
Code mentioned therein acts as the Payment office for affecting
payment of COD Amount.
|
||
BNPL Customer Creation
|
Office creation (if
PBC) &
EBiller ID (if customer wants to avail
COD)
|
The Divl. Administrator of the
Division (both RMS and Postal) can perform this operation by logging into
ParcelNet Website at URL
|
|
Application installation (if it
is a Parcel Booking Centre)
|
Point of sale, RNet communication,
BNPL application available at CEPT ftp site ftp://ptcinfo.org/Meghdoot7/Updates/ParcelNetUpdate29112013/
have to be
installed. The Solutions available therein for the software issues
noticed/observed so far also to be updated.
|
||
Actual Booking
|
Latest office master date
|
Request through RNet communication and
update using Despath module.
Format mentioned for ExcelFile has to
be used for Bulk uploading
|
|
Sorting Office (PH/EPH)
|
Software Installation
|
ParcelNet Client and ParcelNet
Communication software have to be installed afresh. The software can be
downloaded from the CEPT ftp site ftp://ptcinfo.org/Meghdoot7/Updates/ParcelNetUpdate29112013/. Solutions provided so far for the issues which are available
therein should also be updated
|
|
Office master updation
|
Software installation
|
Request for Officemaster and Hubmaster
data from central server and update the same
|
|
Opening of Parcel Bag
|
If virtual Data not received, Article
type selection should be done carefully, as the same data flows to next
office
|
||
Delivery
Office
|
Software upgradation
|
Postman Module and RNet Communication
of the Delivery Office should be upgraded by downloading the
same from CEPT ftp site site ftp://ptcinfo.org/Meghdoot7/Updates/ParcelNetUpdate29112013/. The Solutions available therein for the issues noticed so far
also to be updated.
|
|
Invoicing to Postman (Non COD article)
|
Bag receipt
|
The Barcode validation already
implemented has been removed w.e.f. 18.12.2013. The delivery post
offices who face the problem due to non receipt of valid barcodes
(bag/article) can download the new Postman software available in
SolutionsToParcelNetUpdate from CEPT ftp siteftp://ptcinfo.org/Meghdoot7/Updates/ParcelNetUpdate29112013/and use the same for receiving the bag/invoicing the articles
|
|
Invoicing to postman (COD article)
|
Electronic data from Central Server
|
Once
COD article is booked, Electronic data is transmitted by Central Server to
concerned Delivery Post Office. In case, the delivery post
office has not upgraded by the time of receipt of electronic information,
then it is not possible to invoice the article even though it is physically received. In
such a case, the Post Office need to use option “Request
COD electronic data” available for Postman Supervisor.
Then the electronic data pertaining to the COD articles selected by Postman
supervisor will be transmitted to the Post office again.
|
|
Delivery of Article
|
Correct pincode at the time of Booking
|
If
pincode not matched, the article has to be returned to sender. No
redirection facility is available for COD articles
|
|
Payment details updation in ePayment
system
|
Once
COD article is delivered in postman module, data will be transmitted
internally to epayment system and then e-payment communication will transmit
the delivery particulars to ePayment central server.
|
||
ePayment Server
|
Transmission of data to Payment Office
|
Based
on the Pincode of the Customer entered at the time of COD Customer
registration in ePayment system, the ePayment server transmits the
data of all COD articles delivered across the country to that Payment Office. This
information is automatically available in Treasury module of
|
|
Paymet office
|
Payment of COD amount
|
Upgradation
|
Treasury module and RNet Communication
of the Payment Office should be upgraded by downloading the
same from CEPT ftp site site ftp://ptcinfo.org/Meghdoot7/Updates/ParcelNetUpdate29112013/. The Solutions available therein for the issues noticed so far
also to be updated.
|
No comments:
Post a Comment
Hmmmmm... what are you thinking? Do not forget to comment,It helps us to improve this blog and help us to make better. on